Big Ten Rentals is used to jobs with quick turnaround times, and this event is no different. The call came in late Tuesday asking for enough air conditioning to keep an event in two airplane hangers (~10,000 sq. ft. each) cool on what turned out to be a day in the 90s. The Problem: No accessible doors or windows for supply and return ducts, and the main hanger door needed to continue functioning. The Solution: Create a structure out of scaffolding to hold the A/C duct system and still allow for the hanger door to operate. In total, 250 tons of air conditioning were being pumped into the two hangers: Two 80-ton A/C units and Three 30-ton A/C units. We finished setting up the job around midnight the day before the event began.